Post 16 made on Saturday November 16, 2002 at 19:37 |
JamesJ574 Lurking Member |
Joined: Posts: | November 2002 7 |
|
|
See... On most jobs it turns out that two men means twice as fast, but this just came up recently on a nightmare of a house. this house was designed by some crack head architect. This multi-million dollar house had almost no wire chases, concrete slabs between each floor and steel beabs every where you looked. every pull required two men and the two day two men bid turned into5 days two guys. If it had been one man it would not have been done in anywhere near a reasonable amount of time.
Anyway I guess I wanted to know if anyone out there just uses a crew for roughins and charges a different rate than they would charge for lead installers to do it.
|
|
|