On July 23, 2014 at 21:17, Dave in Balto said...
It would be so nice to be able to tell the builder that the insulation needs to wait because I'm not ready for it.

I have done this.


Had one superintendent have the place insulated on a Friday, and the drywall guys start on Saturday, and I hadn't even begun running wire (I was scheduled for Monday by the builder).

The builder had to have guys come in and remove most of the drywall so all my stuff could go in, which included a central vacuum system.

Super got fired after a couple other idiot mistakes.