Post 4 made on Sunday April 6, 2003 at 00:17 |
Impaqt RC Moderator |
Joined: Posts: | October 2002 6,233 |
|
|
Well, First thing is to do one of two things.....
Schedule the correct amount of time for a given job
OR
Find out why your installers (Or you) are not getting the jobs done in the time your alotting.
I will NOT push back scheduled jobs because a current job added more stuff. We will complete what was scheduled, and if time allows, begin another project or addition, but if there isnt enough time to add those other 2 rooms of speakers, they go to the back of the line (Currently 2-4 weeks with 4 two-man Crews). Of course if time opens up, we do our best to get back sooner.....
|
|
|
|