Your Universal Remote Control Center
RemoteCentral.com
Custom Installers' Lounge Forum - View Post
Up level
Up level
The following page was printed from RemoteCentral.com:

Login:
Pass:
 
 

Original thread:
Post 11 made on Tuesday December 17, 2019 at 09:39
cma
Super Member
Joined:
Posts:
August 2003
3,044
I figure 1 hour per run.

The easy way to figure it out is to track a couple prewires. Look at the amount of time it takes from the time that your workers clock in to the time they clock out and at the end of the prewire stage divide their time by the number of drops. Once you get that number add on 15-20% to cover any oddball stuff that may happen and I bet you come out to roughly 1 hour per drop.


Hosting Services by ipHouse