On September 17, 2017 at 13:57, gerard143 said...
how long did the project in the video take you?
Planning started early 2013
Ground breaking was Spring 2014
Rough-in started July 2014
Substantial completion was October 2016
Clients first stayed at the property June 2017
The home has been in a constant state of changes, upgrades, remodel, etc. since October last year and the clients have only stayed there for 5-6 weeks total.
Here's the breakdown for labor if that's what you're interested in:
127hrs - Design & project management
493hrs - Rough-in, installation, programming & testing
87hrs - Additional work outside the original proposal billed T&M